800 t/h Limestone Aggregate Crushing Plant

Reviewed 2026-11-27 Bellian Process Engineering

A three-stage 800 t/h limestone plant producing 0-5, 5-10, 10-20 and 20-31.5 mm aggregate, with 62% of output in the 10-20 mm fraction and dust held under 20 mg/m3.

800 t/h Limestone Aggregate Crushing Plant

A 800 t/h limestone plant is not simply a scaled-up 300 t/h line. Above roughly 500 t/h the bottleneck moves from the crusher to the screen deck, and the layout has to be arranged so that material falls once instead of being lifted twice. This route is the configuration we build most often for quarry operators supplying ready-mix concrete and asphalt plants within a 60 km radius.

Capacity800 t/h (0-31.5 mm)
Max feed800 mm
Products4 graded fractions
ScopeDesign, supply, commissioning

What the line has to handle

Limestone from a bench blast typically arrives at 0-800 mm with 2-4% moisture and a Bond work index around 10-12 kWh/t. It is soft enough that impact crushing is cheaper than cone crushing on wear cost per tonne, but abrasive silica stringers appear in most deposits and will shorten blow bar life if the rotor speed is set for maximum reduction ratio. We size the primary on the 95th percentile block, not the average, because one 1.1 m block per shift is enough to stall a machine sized on the mean.

Process flow

Hopper + vibrating feederPrimary jawPre-screenSecondary impactFinal screenStockpile conveyors

Stage 1 — primary crushing

A 60 m3 receiving hopper with a 1,400 mm grizzly feeds a ZSW-600x180 vibrating feeder, which scalps minus 80 mm to a bypass conveyor before the crusher. Bypassing this fraction is worth roughly 15% of the primary's throughput and is the single cheapest capacity gain on a limestone line. The PE-1200x1500 jaw crusher is set at 150 mm close side, giving a product of 0-250 mm at 800 t/h with a 250 kW drive.

Stage 2 — pre-screening and secondary crushing

Primary product reports to a double-deck pre-screen. Undersize goes straight to the final screen, which removes 35-40% of the tonnage from the secondary circuit. Oversize feeds two PF-1520 impact crushers running in parallel at 400 t/h each. Two smaller units rather than one large unit keeps the plant running at half capacity during rotor maintenance, which matters more than the small saving in capital cost.

Stage 3 — final screening and stockpiling

Two 3YKR-2460 circular vibrating screens operate in parallel, each 6 m long and 2.4 m wide, with polyurethane decks on the 5 mm cut. Screen area is deliberately 20% above the calculated requirement: a limestone plant running 16 hours a day will blind a 5 mm deck within four months, and the spare area keeps the product in spec until the deck is changed.

Four B1000 belt conveyors discharge to radial stockpiles of 15,000 t total live capacity.

Equipment list

StageEquipmentQtyPower
FeedingZSW-600x180 vibrating feeder12 x 37 kW
PrimaryPE-1200x1500 jaw crusher1250 kW
Pre-screening2YKR-2160 pre-screen130 kW
SecondaryPF-1520 impact crusher22 x 250 kW
Final screening3YKR-2460 vibrating screen22 x 45 kW
ConveyingB1000 belt conveyor, 480 m total9185 kW
Dust controlDMC-400 pulse jet bag filter215 kW

Installed power is about 1,840 kW. With a load factor of 0.78 the running draw sits near 1,430 kW, which is 1.8 kWh per tonne of finished product — a figure worth checking against your electricity tariff before choosing between impact and cone crushing.

Product gradation

FractionShare of outputTypical use
0-5 mm32%Concrete sand, asphalt filler
5-10 mm18%Chip seal, precast
10-20 mm38%Ready-mix coarse aggregate
20-31.5 mm12%Base course, drainage

The 10-20 mm share is what most concrete customers pay a premium for. If your deposit runs high in fines, adding a spiral sand washer after the final screen will move 4-6% of the 0-5 mm fraction into a saleable washed sand instead of letting it leave as waste.

Layout and site requirements

The line fits a footprint of 85 x 45 m on level ground, or a terraced layout on a hillside where the primary sits at the top bench and the stockpiles at the bottom — the second option removes two conveyors and about 120 kW from the total. Foundation loads peak at 4.2 t/m2 under the jaw crusher. Water consumption is limited to dust suppression, roughly 8 m3 per day.

Questions we are asked before quoting

Can the same plant make 0-5 mm manufactured sand?

Yes, with a fourth stage. A VSI Sand Making Machine and a sand washing unit after the final screen convert part of the 5-20 mm flow into 0-5 mm with a fineness modulus of 2.6-2.9. Expect to trade 15-20% of coarse output for the additional sand.

What happens if the feed turns out wetter than expected?

Above 6% moisture the 5 mm deck will blind and the belt will carry back. The fix is a heated deck or a smaller cut point, not a bigger screen. We ask for a moisture sample before finalising the layout for this reason.

How long is delivery and installation?

Twelve to fourteen weeks for manufacture, four to six weeks for erection and commissioning with our supervisor on site. The plant is shipped as 22 containers or in break bulk, depending on the port.

Other solution categories

Same engineering team, different process route.

Send your material. We will send the flow sheet.