Henan Bellian Mining Machinery
Waste & Slag Recycling · Process route

Carbide Slag Utilization Line

Reviewed 2026-11-27 Bellian Process Engineering

PVC plants discharge 1.5-2 tonnes of carbide slag per tonne of resin at 60% water. Dewatering, drying and the cement route that turns a slurry into a limestone substitute.

Carbide Slag Utilization Line

Carbide slag is what remains after calcium carbide reacts with water to make acetylene for PVC. Chemically it is 85-92% calcium hydroxide with a little carbon and silica; physically it is a 40-60% water slurry with a particle size finer than 100 micron, which makes it one of the most difficult materials to dewater and one of the best limestone substitutes available to a cement plant next door.

Capacity200-2,000 t/d wet
Ca(OH)285-92%
Water in40-60%
Water out< 1%

Why it cannot simply be dried

The slurry is thixotropic and blinds filter media. Thermal drying of a 60% water slurry costs 1.2-1.5 GJ per tonne of dry solids, which is more than the material is worth as limestone. Every viable carbide slag plant starts with mechanical dewatering, because removing water mechanically costs a hundredth of what removing it thermally costs.

StageMethodMoisture outEnergy
ThickeningGravity thickener with flocculant60% to 45%Negligible
Mechanical dewateringFilter press or belt press45% to 25%20-40 kWh/t dry
Thermal dryingRotary dryer with lifters25% to 1%1,600-2,000 kJ/kg water

Process flow

Slurry from plantThickenerFilter pressRotary dryerGrindingCement raw meal

Dehydration

A gravity thickener with anionic flocculant brings the slurry from 60% to 45% water. A membrane filter press then takes it to 22-28% cake, which is the practical limit for this material because the particles are too fine and too compressible for a belt press to do better. Cake at 25% water can be conveyed and fed to a dryer without sticking.

Drying

A rotary dryer with internal lifters and a flighted section, inlet gas at 600-700 C, outlet material at 90-110 C. Carbide slag is alkaline and slightly corrosive when wet; the dryer shell should be mild steel with a wear liner and the ducting stainless. Calcium hydroxide starts to decompose to CaO above 450 C, so the material temperature must stay below 400 C — a dryer that runs too hot produces a product that has already lost its reactivity and is no longer a limestone substitute.

Use in cement

Dried carbide slag substitutes for limestone in the raw meal. The advantage is large: limestone must be decarbonated at 890 C using 1,780 kJ per kg, while carbide slag is already Ca(OH)2, which decomposes at 550 C using 1,100 kJ per kg. The kiln heat consumption drops by 40-70 kcal per kg of clinker when 8-15% of the raw meal is carbide slag. This is the single strongest economic argument for the plant, and it only works if the cement plant is within 30-50 km.

Equipment list

StageEquipmentSpecification
ThickeningThickener, 12 m diameterWith flocculant dosing
DewateringMembrane filter press, 200 m2To 25% moisture cake
DryingRotary dryer 2.4 x 20 mTo below 1%, product below 400 C
Dust collectionBag filter99.9%
StorageSealed siloMoisture protected
ConveyingEnclosed belt or air slideTo raw meal proportioning

The alternative: make lime from it

Carbide slag can be calcined back to quicklime at 900-1,000 C, which closes a loop for a PVC producer that buys lime. The economics depend entirely on the fuel price against the delivered lime price; where both are favourable the plant pays back in three to four years. The catch is the chloride and sulphide content, which limits how much can be fed to a kiln before the refractory and the bag filter suffer.

Questions we are asked before quoting

Can carbide slag be used as a cement set accelerator?

No. It is calcium hydroxide, which is already the product of cement hydration; adding it does not accelerate set and it increases water demand.

What is the disposal cost if I do nothing?

Landfill of a 60% water alkaline slurry is 15-40 USD per tonne in most jurisdictions, plus the long-term liability. That figure alone usually justifies the dewatering plant.

Other solution categories

Same engineering team, different process route.

Send your material. We will send the flow sheet.

Feed size, moisture, target capacity and product spec are enough to start. Quotations and plant layouts are free and usually back within one working day.

Request a flow sheet WhatsApp us