Nickel Laterite Ore Preparation Line

Reviewed 2026-11-27 Bellian Process Engineering

Laterite ore at 30-35% moisture, 1.5-2.2% nickel, and two very different routes: RKEF smelting needs dry lump, HPAL needs fine slurry. The preparation plant decides which one is possible.

Nickel Laterite Ore Preparation Line

Nickel laterite is a wet, sticky, low-grade ore and almost all of its processing cost is decided before the metallurgical plant. The ore comes out of a tropical pit at 30-35% moisture with a clay fraction that blinds screens and plugs chutes. Two industrial routes consume it — rotary kiln electric furnace smelting, which needs dry and sized feed, and high-pressure acid leach, which needs a fine slurry — and they impose opposite requirements on the preparation plant.

Capacity500-5,000 t/d
Ni grade1.5-2.2%
Moisture in30-35%
Moisture out< 20% (RKEF)

Two ore types in one deposit

HorizonNiFeMgORoute
Limonite (upper)1.2-1.6%40-50%2-5%HPAL, or iron-nickel
Saprolite (lower)1.8-2.5%12-20%15-25%RKEF smelting

The two horizons need to be mined and stockpiled separately. Blending them and feeding a single stream to the smelter is the most common and most expensive mistake in a laterite operation: the saprolite needs high temperature and the limonite generates too much slag, and the furnace responds by running badly on both.

Process flow

PitStockpile by typeHopperRoll crusherWet screenDewateringDryerSized ore to kiln

Crushing in sticky ore

Laterite at 32% moisture does not flow through a jaw crusher; it packs. The usual solution is a single-roll or mineral sizer with a toothed rotor that tears rather than compresses, or a jaw crusher with a specially profiled chamber and a vibrating feeder that keeps the material moving. Washing the feed with high-pressure water before crushing converts the problem into a slurry problem, which is easier but adds water treatment.

Screening at high moisture

A conventional vibrating screen blinds within hours on laterite. Wet screening with spray water at 1-2 mm works; dry screening only works below 20% moisture. Some plants use a trommel with internal water sprays, which tolerates sticky feed better than a flat deck because the rotation keeps the apertures clear.

Drying for RKEF

A rotary dryer at 400-500 C inlet gas brings the ore from 32% to 18-20%, which is the feed condition for a rotary kiln. Drying below 15% is not necessary and costs fuel, because the kiln will drive off the balance anyway. Laterite dryers are large — a 5,000 t/d operation needs a 4 x 32 m dryer — and they are the single largest fuel consumer in the preparation plant.

Equipment list

StageEquipmentSpecification
FeedingApron feeder with variable speed2,000 t/d
CrushingMineral sizer, toothedTo 150 mm, sticky duty
ScreeningTrommel with water sprays2 mm cut, 60% solids
DewateringDewatering screenTo 25% moisture
DryingRotary dryer 4 x 32 mTo 18-20% moisture
Dust and fumeBag filter, cycloneDryer exhaust
StockpileCovered shedRain adds 3-5% moisture

The moisture that is invisible on the specification

Laterite in a tropical stockpile gains 3-5% moisture in a single monsoon week. A dryer sized on the annual average will be the bottleneck for four months a year, and a smelter that receives wet ore cuts its feed rate to protect the kiln. Size the dryer on the wet-season moisture, not the annual mean; the capital difference is 15% and the production difference is 20%.

Questions we are asked before quoting

Can the same plant feed RKEF and HPAL?

Only the mining and stockpiling can be shared. RKEF needs dry sized lump and HPAL needs a slurry ground below 1 mm, which are different circuits.

What nickel grade makes laterite viable?

Above 1.8% for RKEF at current energy prices, above 1.2% for HPAL where the cobalt credit helps. Below 1.2% the ore is a construction material, not an ore.

Other solution categories

Same engineering team, different process route.

Send your material. We will send the flow sheet.

Feed size, moisture, target capacity and product spec are enough to start. Quotations and plant layouts are free and usually back within one working day.

Request a flow sheet WhatsApp us